Plan Check Requirements:
In order to avoid additional project review costs, construction delays, and/or potential liabilities, it is imperative for you, as the developer, to:
- Review and discuss your project schedule with LBWD as soon as possible; and
- Select a qualified consultant experienced in the design of water and/or sewer improvement projects
The plan check process includes, but is not limited to, the following:
- Your engineer submits the first plan check consisting of two (2) sets of check prints (minimum)
- Allow 3 to 4 weeks for review of the first plan check, and 1 to 2 weeks for subsequent plan check reviews
- Your engineer submits for review, calculations supporting the water system network design, water consumption, irrigation system demands, and Long Beach Fire Department (LBFD)‐approved fire flow requirements
- All LBWD‐approved drawings for public water and/or sewer facilities will be drafted on 22 x 34 inch mylars showing both plan and profile
- Your engineer will submit “As‐Builts” or Record Drawings to LBWD at the completion of your project, both in hard (paper) and electronic (AutoCAD) copy